Starting point of gite renovation and latest picture of progress with floorplans of each gite. Click on each image for a larger picture.
View a timelapse of the renovation in pictures. Broadband users only.
| December 2004 | ||||||
| Sun | Mon | Tue | Wed | Thu | Fri | Sat |
| 1 | 2 | 3 | 4 | |||
| 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 19 | 20 | 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 | 31 | |
| Nov Jan | ||||||
October 2004
November 2004
December 2004
January 2005
February 2005
March 2005
April 2005
May 2005
June 2005
July 2005
August 2005
September 2005
October 2005
December 2005
January 2006
February 2006
March 2006
April 2006
May 2006
November 2006
Lucarnes roofed
Our roofers arrived a week early, which I'm very pleased about. They have been at it for a couple days and finished both the lucarnes now except the ridge tiles. Each slate tile is attached to the battens with a stainless steel 'double' hook. One end hooks over the batten and the other end clips under the bottom edge of the tile. All the gullies and rain channels are done in zinc flashing, same as the guttering and down pipes. Everything gets soldered up on site to fit.
They are currently tiling the new kitchen roof. It should be much simpler as it's just are large flat area.
1:24:51 PM